Refits carried out by Integrated Marine Group to date
S.Y. Zenji
56m Perini Navi Ketch
March 2009 to September 2009
Delivered October 2009
This was a large scale project with works that included: Conducting the 5 year ABS Survey; a full repaint including rigs; interiors refurbished; new entertainment systems; extensive engineering and systems work; mast & rigging overhaul; decking and on deck systems and plenty more.
M.Y. Tigre Dor
55m Amels
February 2009 to April 2009
Our works included: 10 Year Lloyds engineering survey; Routine maintenance Slipway period in Whangarei; Teak deck recaulking and yacht interiors work; hull paint touch ups; engineering and electrical systems works.
M.Y. Karima
49m Amels
October 2007 to February 2009
Undertook refit works during two repair periods; the owners took a trip around Northland coasts during summer 2007 between works.
The works carried out included: fitting a new Quantum stabiliser system into existing fuel tanks; Caterpillar main propulsion generator overhauls; ABB electric propulsion and drive system works; interiors; helideck; hydraulic systems; plumbing & ventilating systems; alarm & monitoring systems; interiors crew cabins; crew mess; saloon and guest cabins; galley systems; bridge systems; new teak decking; new helicopter deck; tender works; tank cleaning; Lloyds survey and certification works ( 15 year survey ); a new custom built 10m tender.
The helicopter was reloaded January 2009 during seatrials and the vessel departed for French Polynesia February 2009 after a challenging but very successful works period.
M.Y. Yaakun
65m Cantilerri
June 2007 to September 2007
20 year Lloyds survey inspection and repairs; galley systems refit; design and install of new walk in fridge freezer; full hull paint with new colour on the Titan Marine Slipway in 8 weeks; interiors furnishing and decor refresh in master guest and saloon spaces; MTU main engine 20 year survey; rebuild MTU generators; steering systems; stabilizers; new fresh water systems; purifier overhauls; tank cleaning and reconfiguration to suit new installed Hamann system; air conditioning systems maintenance; two custom made wine cellars in saloon; new bar unit fitted to saloon; overhaul & repaint deck cranes; teak decking works; new deck lockers; crew cabin refurbishment; upper deck paint repairs.
M.Y. Black Pearl
70ft Betram
January 2010 to March 2010
This short project was focused mainly on aesthetics. The Saloon and Master Cabin were stripped of the 1970s look and rebuilt to a more modern taste whilst the remaining cabins and galley had some touch ups. Other works included: complete repower to 230v; paint transom and hull lines; replace toilet systems; service of both main engines and generators. Read more on this refit by following this link ....
S.Y. Runaway Bunny
74ft Sloop – JFA Shipyards
September 2009 to March 2010
A small project for Integrated Marine Group which kept the boat building team occupied for a few months. Integrated Marine Group looked after the new teak decking and the installation and design of a new switchboard, whilst the boat was repainted, had its rig overhauled and painted, along with interior works as necessary.